Japan Nuclear Fuel skipped safety checks at Rokkasho plant for 14 years via Japan Times

Nuclear regulators concluded Wednesday that Japan Nuclear Fuel Ltd. violated legally binding safety rules by failing to conduct necessary checks for over a decade at its uncompleted spent nuclear fuel reprocessing plant in the country’s northeast.

The failure of checks at an underground portion of the plant in the village of Rokkasho in Aomori Prefecture for about 14 years eventually resulted in about 800 liters of rainwater flowing into a building housing an emergency diesel generator in August this year. The generator is a crucial device in times of crisis such as the loss of external power.

Japan Nuclear Fuel President Kenji Kudo said at a Nuclear Regulation Authority’s meeting that he will prioritize inspections of all facilities at the plant and suspend its operations to seek a safety approval on the plant to put it on stream.

The utility plans to check its facilities and some 600,000 devices by the end of this year before requesting the authority to resume its safety assessment for the plant.

The body applied for a safety assessment of the plant in 2014 and aimed to complete it in the first half of fiscal 2018, but the goal is likely to be delayed due to the need for inspections.

The envisioned nuclear fuel reprocessing plant is a key component of the government’s nuclear fuel recycle policy, which aims to reprocess spent uranium and reuse extracted plutonium and uranium as reactor fuel.

[…]

 

Read more.