Fukushima No. 1 plant’s ice wall won’t be watertight, says chief architect via The Japan Times

Coping with the vast amounts of groundwater flowing into the broken Fukushima No. 1 nuclear plant — which then becomes irradiated and seeps back out — has become such a problem that the country is building a ¥35 billion “ice wall” into the ground around it.

Even if the frozen barrier built with taxpayers’ money works as envisioned, it will not completely block all water from reaching the damaged reactors because of gaps in the wall and rainfall, creating as much as 50 tons of tainted water each day, said Yuichi Okamura, a chief architect of the massive project.

[…]
epco resorted to devising the 1.5-km-long (1-mile-long) ice wall around the facility after it became clear it had to do something drastic to stem the flow of groundwater into the facility’s basement and keep contaminated water from flowing back out.

“It’s a vicious cycle, like a cat-and-mouse game,” Okamura said of the water-related issues. “We have come up against many unexpected problems.”

The water woes are just part of the many obstacles involved in controlling and dismantling the Fukushima plant, a huge task that will take 40 years. No one has even seen the nuclear debris. Robots are being created to capture images of the debris. The radiation is so high no human being can do that job.

The ice wall, built by construction company Kajima Corp., is being turned on in sections for tests, and the entire freezing process will take eight months since it was first switched on in late March. The entire wall requires as much electricity as would be needed to power 13,000 Japanese households.
[…]
But critics say the problem of the groundwater reaching the reactors was a no-brainer that should have been projected.

Building a concrete wall into the hill near the plant right after the disaster would have minimized the contaminated water problem considerably, says Shigeaki Tsunoyama, honorary professor and former president of University of Aizu in Fukushima.

Even at the reduced amount of 50 tons a day, the contaminated water produced at Fukushima will equal what came out of Three Mile Island’s total in just eight months because of the prevalence of groundwater in Fukushima, he said.

Although Tepco has set 2020 as the goal for ending the water problems, Tsunoyama believes that’s too optimistic.

“The groundwater coming up from below can never become zero,” he said in a telephone interview. “There is no perfect answer.”

Okamura acknowledged the option to build a barrier in the higher elevation near the plant was considered in the early days after the disaster. But he defended his company’s actions.

The priority was on preventing contaminated water from escaping into the Pacific Ocean, he said. Various walls were built along the coastline, and radiation monitors show leaks have tapered off over the last five years

Opponents say the ice wall is a waste of taxpayers’ money and that it may not work. “From the perspective of regular people, we have serious questions about this piece of research that’s awarded a construction giant,” said Kanna Mitsuta, director of ecology group Friends of the Earth Japan.

“Our reaction is: Why an ice wall?”

PHOTOS
search iconCLICK TO ENLARGE

Journalists look at storage tanks filled with radioactive water at the tsunami-crippled Fukushima No. 1 nuclear power plant in the town of Okuma, Fukushima Prefecture, in February. | AP

KEYWORDS
3/11, FUKUSHIMA NO. 1, ICE WALL, NUCLEAR ENERGY, NUCLEAR POWER

NATIONAL
4,024 Japanese, 90 non-Japanese in line for government’s spring decorationsJapan makes shinkansen safety pitch in bid for Malaysia-Singapore rail contractJapan pushes for basic AI rules at G-7 tech meetingKumamoto kicks off housing drive for evacuees; Kyushu Expressway reopens

Read more.

This entry was posted in *English and tagged , . Bookmark the permalink.

Leave a Reply