Tokyo Electric Power Co. Holdings Inc. decided on Oct. 28 to provide financial support to the aging Tokai No. 2 nuclear plant, which has been offline since the 2011 earthquake and tsunami disaster and faces an uncertain future.
TEPCO’S board agreed on the assistance estimated at more than 220 billion yen ($2 billion).
Japan Atomic Power Co., which owns the nuclear plant in Ibaraki Prefecture, will accelerate the construction of anti-tsunami embankments around the plant and other safeguards to full speed.
But local municipalities have opposed the resumption of operations at the Tokai No. 2 plant, where safety upgrades are needed, and an agreement to gain their consent is nowhere in sight.
TEPCO faces the serious risk of failing to recoup its enormous investment in the Tokai No. 2 plant.
“We have reached a conclusion that we can expect the Tokai No. 2 nuclear plant to be a source of power that helps provide inexpensive and stable electricity that emits less carbon dioxide to customers,” Rikuo Ohtsuki, a managing executive officer at TEPCO, said at a news conference on first-half financial results.
Ohtsuki, however, declined to offer specifics such as the amount of financial assistance and the purchase price of electricity from Japan Atomic Power.
TEPCO has been virtually nationalized with an injection of taxpayer money since the 2011 disaster at its Fukushima No. 1 nuclear power plant.
For such an entity to spend a vast sum to assist another nuclear plant operator has elicited criticism from the public and experts, who have urged TEPCO to be accountable and justify the decision.
[…]
Japan Atomic Power has formally acknowledged the costs of the construction of safety measures at the Tokai No. 2 plant and anti-terrorism facility will total 235 billion yen.
To recoup such an investment outlay, the selling price of electric power per kilowatt hour will need to be raised to about 14.5 yen, according to an estimate by CNIC.
In the most recent spot electric power market, the selling price of electric power was a little under 10 yen per kilowatt hour.
The new estimate is almost 1.5 times higher.
“The price would be much higher than the market rate, which will increase the burden on consumers,” Matsukubo said.
MANAGERIAL CRISIS AT TEPCO
Japan Atomic Power is a pioneer in nuclear power, starting with the operation of the Tokai nuclear plant in Ibaraki Prefecture in 1966, the nation’s first commercial reactor.
Nine regional utilities, which produce nuclear power, like TEPCO, and the Electric Power Development Co. have contributed about 90 percent of the capital.
Together they have promoted technical cooperation, symbolizing the nation’s nuclear power industry.
TEPCO is the largest shareholder of Japan Atomic Power, controlling about 28 percent.
But Japan Atomic Power faces a tough management environment. It owns four nuclear reactors—Tokai, Tokai No. 2, Tsuruga No. 1 and Tsuruga No. 2.
Of these, Tokai and Tsuruga No. 1 are being decommissioned.
Tsuruga No. 2 in Fukui Prefecture has suspended operations since the Fukushima nuclear disaster, and it has been suspected that an active fault runs directly under its nuclear reactor building.
If the company fails to resume operations of Tokai No. 2, bankruptcy is likely.
[…]
Many have urged TEPCO to use the financial leeway it is investing in the Tokai No. 2 plant to compensate victims of the Fukushima No. 1 plant disaster and lower electricity rates.
(This article was written by Rintaro Sakurai, Hiroki Ito and Toshio Kawada.)