Nuclear plant operators must pay price for missing deadline via The Asahi Shimbun

Recent announcements by three electric utilities that they will miss the deadline for taking legally required anti-terrorism measures for their nuclear power plants raises serious questions about their commitment to nuclear safety.

Kansai Electric Power Co., Kyushu Electric Power Co. and Shikoku Electric Power Co. said on April 17 that they will miss the deadline for completing the facilities to respond to emergencies triggered by terrorist attacks against their reactors. The reactors include ones that have been restarted after being shut down following the 2011 Fukushima nuclear disaster.

The companies have asked the Nuclear Regulation Authority to extend the deadline.

The facilities in question are supposed to be at the forefront of efforts to prevent severe nuclear accidents in the event their reactors come under terrorist attacks using aircraft.

The utilities should not be permitted to continue their operations until this crucial safety aspect is fixed.

We call on the nuclear safety watchdog to take a firm stand toward their request.

Nuclear plant operators are required to erect anti-terrorism facilities under new nuclear safety standards that took effect in 2013. The regulations are modeled on measures to deal with the risk of terror attacks against nuclear plants worked out by the U.S. Nuclear Regulatory Commission following the Sept. 11 attacks against the United States in 2001.

The principal objective of the measures is to prevent the kind of nuclear meltdowns that occurred at the Fukushima No. 1 nuclear power plant in 2011 even if the control room is destroyed by an aerial terror attack.

The new regulations require the operator of a nuclear plant to build anti-terror response facilities, including an emergency control room and a power generator located 100 meters or more from the control room. The emergency response facilities should be capable of cooling the reactors even if the control room becomes disabled.

The three companies told the NRA that completing the facilities for 12 reactors at their six nuclear plants will not be completed until one to two and a half years after the respective deadlines. They cited the scale of the project and difficulty of the construction work for the delays.

But the deadline has already been extended once. The initial deadline for the construction of the required facilities was 2018, five years after the new safety standards took effect.

[…]

Read more.

This entry was posted in *English and tagged , . Bookmark the permalink.

Leave a Reply