Work began in recent days to remove, bit by bit, the giant chimney protruding from the Chernobyl nuclear power station. It’s one small part of a mammoth engineering project, now nearing completion, designed to slash the risk of another major release of radioactivity.
Massive and glittering in the weak winter sunshine, a half-built arch looms over Chernobyl’s decaying industrial landscape of cooling towers and power lines.
One of the biggest engineering projects in history, it has been likened to a gigantic metal igloo, built to seal off hundreds of tons of nuclear fuel and dust buried inside reactor number four, which in 1986 blew up and burned for 10 days.
Everything about the project is epic: the size, the 1.5bn euro (£1.2bn) cost, the technical problems of working on a radioactive building site.
At 110m (360ft) tall, the structure could house the Statue of Liberty, and at 257m (843ft) wide, there would be room for a football pitch. There are acres of metal panels in the roof, to seal off the reactor and the dangerous mess inside. The whole lot will be held together by 680,000 heavy bolts.
With these gigantic dimensions the arch would be difficult to build anywhere, but it is being assembled in one of Europe’s more remote corners, a site surrounded by forest and marsh in northern Ukraine, far from the factories of Western Europe where its component parts are made. This autumn, as the project reached the half-way point, it was more than a decade behind schedule, although engineers believe work will now go more quickly and it could be finished in 2015.