Fukushima dome roof takes shape, but radiation remains high via The Asahi Shimbun

High radiation levels are still limiting recovery work at the Fukushima No. 1 nuclear plant, a stark reality that reporters saw firsthand when they observed efforts to remove risk factors there.

Media representatives were invited into the plant in early December to see construction work, with the building of a domed roof over the No. 3 reactor building as the main focus.

However, they were only allowed to stay on top of the roof for 20 minutes due to high radiation levels.

The roof is being put together directly above the storage pool for spent fuel. The dome is designed to prevent the spewing of radioactive materials when the fuel is actually removed from the pool.

[…]

Although the dome will help prevent the spread of radioactive materials, building parts and other debris as well as some equipment have still not been completely removed from the storage pool, which holds 566 fuel rods.

The collapsed roof and walls were removed to allow for the construction of the domed roof, which began in the summer. The domed roof is about 17 meters high, and a crane was also installed under it in November.

Plans call for the removal of the spent fuel from the No. 3 building to begin in the middle of the next fiscal year.

Internal radiation exposure levels were measured before media representatives headed to the No. 3 reactor building. They were also required to don protective clothing as well as a partial face mask covering the mouth and nose from about 100 meters from the building.

Radiation levels close to the building were 0.1 millisieverts per hour.

[…]

To the south of the No. 3 reactor building stands the No. 4 reactor building, from where all the spent nuclear fuel has been removed.

[…]

The radiation level near the pool was 0.68 millisieverts per hour. While that was a major improvement from the 800 millisieverts per hour recorded in the immediate aftermath of the nuclear accident close to seven years ago, it was still too high to allow for a stay of longer than 20 minutes.

Read more at Fukushima dome roof takes shape, but radiation remains high

This entry was posted in *English and tagged , , , . Bookmark the permalink.

Leave a Reply