Featured Topics / 特集
-
A nuclear power plant in Byron, Illinois. Taken by photographer Joseph Pobereskin (http://pobereskin.com). カレンダー
October 2024 S M T W T F S 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 -
Latest Posts / 最新記事
- 被ばく研究の灯は消さない 国や自治体が「風化待ち」の中、独協医科大分室が移転してまで続ける活動の意義via東京新聞 2024/10/05
- Chernobyl-area land deemed safe for new agriculture via Nuclear Newswire 2024/09/26
- 長崎「体験者」の医療拡充 なぜ被爆者と認めないのか【社説】via 中国新聞 2024/09/23
- Three Mile Island nuclear plant will reopen to power Microsoft data centers via NPR 2024/09/20
- Tritium into the air? via Beyond Nuclear International 2024/09/18
Discussion / 最新の議論
- Leonsz on Combating corrosion in the world’s aging nuclear reactors via c&en
- Mark Ultra on Special Report: Help wanted in Fukushima: Low pay, high risks and gangsters via Reuters
- Grom Montenegro on Duke Energy’s shell game via Beyond Nuclear International
- Jim Rice on Trinity: “The most significant hazard of the entire Manhattan Project” via Bulletin of Atomic Scientists
- Barbarra BBonney on COVID-19 spreading among workers on Fukushima plant, related projects via The Mainichi
Archives / 月別アーカイブ
- October 2024 (1)
- September 2024 (5)
- July 2024 (4)
- June 2024 (3)
- March 2024 (1)
- February 2024 (6)
- January 2024 (4)
- November 2023 (8)
- October 2023 (1)
- September 2023 (7)
- August 2023 (5)
- July 2023 (10)
- June 2023 (12)
- May 2023 (15)
- April 2023 (17)
- March 2023 (20)
- February 2023 (19)
- January 2023 (31)
- December 2022 (11)
- November 2022 (12)
- October 2022 (7)
- September 2022 (6)
- August 2022 (22)
- July 2022 (29)
- June 2022 (15)
- May 2022 (46)
- April 2022 (36)
- March 2022 (47)
- February 2022 (24)
- January 2022 (57)
- December 2021 (27)
- November 2021 (32)
- October 2021 (48)
- September 2021 (56)
- August 2021 (53)
- July 2021 (60)
- June 2021 (55)
- May 2021 (48)
- April 2021 (64)
- March 2021 (93)
- February 2021 (69)
- January 2021 (91)
- December 2020 (104)
- November 2020 (126)
- October 2020 (122)
- September 2020 (66)
- August 2020 (63)
- July 2020 (56)
- June 2020 (70)
- May 2020 (54)
- April 2020 (85)
- March 2020 (88)
- February 2020 (97)
- January 2020 (130)
- December 2019 (75)
- November 2019 (106)
- October 2019 (138)
- September 2019 (102)
- August 2019 (99)
- July 2019 (76)
- June 2019 (52)
- May 2019 (92)
- April 2019 (121)
- March 2019 (174)
- February 2019 (146)
- January 2019 (149)
- December 2018 (38)
- November 2018 (51)
- October 2018 (89)
- September 2018 (118)
- August 2018 (194)
- July 2018 (22)
- June 2018 (96)
- May 2018 (240)
- April 2018 (185)
- March 2018 (106)
- February 2018 (165)
- January 2018 (241)
- December 2017 (113)
- November 2017 (198)
- October 2017 (198)
- September 2017 (226)
- August 2017 (219)
- July 2017 (258)
- June 2017 (240)
- May 2017 (195)
- April 2017 (176)
- March 2017 (115)
- February 2017 (195)
- January 2017 (180)
- December 2016 (116)
- November 2016 (115)
- October 2016 (177)
- September 2016 (178)
- August 2016 (158)
- July 2016 (201)
- June 2016 (73)
- May 2016 (195)
- April 2016 (183)
- March 2016 (201)
- February 2016 (154)
- January 2016 (161)
- December 2015 (141)
- November 2015 (153)
- October 2015 (212)
- September 2015 (163)
- August 2015 (189)
- July 2015 (178)
- June 2015 (150)
- May 2015 (175)
- April 2015 (155)
- March 2015 (153)
- February 2015 (132)
- January 2015 (158)
- December 2014 (109)
- November 2014 (192)
- October 2014 (206)
- September 2014 (206)
- August 2014 (208)
- July 2014 (178)
- June 2014 (155)
- May 2014 (209)
- April 2014 (242)
- March 2014 (190)
- February 2014 (170)
- January 2014 (227)
- December 2013 (137)
- November 2013 (164)
- October 2013 (200)
- September 2013 (255)
- August 2013 (198)
- July 2013 (208)
- June 2013 (231)
- May 2013 (174)
- April 2013 (156)
- March 2013 (199)
- February 2013 (191)
- January 2013 (173)
- December 2012 (92)
- November 2012 (198)
- October 2012 (229)
- September 2012 (207)
- August 2012 (255)
- July 2012 (347)
- June 2012 (230)
- May 2012 (168)
- April 2012 (116)
- March 2012 (150)
- February 2012 (198)
- January 2012 (292)
- December 2011 (251)
- November 2011 (252)
- October 2011 (364)
- September 2011 (288)
- August 2011 (513)
- July 2011 (592)
- June 2011 (253)
- May 2011 (251)
- April 2011 (571)
- March 2011 (494)
- February 2011 (1)
- December 2010 (1)
Top Topics / TOPトピック
- anti-nuclear
- Atomic Age
- Capitalism
- East Japan Earthquake + Fukushima
- energy policy
- EU
- France
- Hanford
- health
- Hiroshima/Nagasaki
- Inequality
- labor
- Nuclear power
- nuclear waste
- Nuclear Weapons
- Radiation exposure
- Russia/Ukraine/Chernobyl
- Safety
- TEPCO
- U.S.
- UK
- エネルギー政策
- メディア
- ロシア/ウクライナ/チェルノブイリ
- 健康
- 公正・共生
- 兵器
- 再稼働
- 労働における公正・平等
- 原子力規制委員会
- 原発推進
- 反原発運動
- 大飯原発
- 安全
- 広島・長崎
- 廃炉
- 東京電力
- 東日本大震災・福島原発
- 汚染水
- 米国
- 脱原発
- 被ばく
- 資本主義
- 除染
- 食の安全
Choose Language / 言語
Tag Archives: 工程
福島第1廃炉、燃料搬出31年までに完了 工程表改定 via 日本経済新聞
政府は2日、東京電力福島第1原子力発電所の廃炉に関する会合を開き、廃炉工程表の改定案を示した。建屋内のプールに残る使用済み核燃料を2031年末までに全て取り出す目標を新たに掲げた。事故後30~40年とする廃炉の完了時期は維持した。廃炉作業で最難関とされる溶融燃料(デブリ)の取り出しは21年に2号機から始める。ただ既に工程に遅れが生じ、直近ではトラブルが相次いでいる。 11年の東日本大震災の影響で福島第1原発は1~4号機で水素爆発や炉心溶融(メルトダウン)を起こした。東電は11年12月に政府が作った廃炉工程表に基づいて廃炉作業を進めている。工程表は約2年に1度改定しており、17年9月以来となる。費用は廃炉だけで約8兆円と政府は試算している。今回、41~51年までの廃炉完了時期は維持した。 […] 改定案は1~6号機の原子炉建屋のプールに残る使用済み燃料を31年末までに取り出すことを明記した。当初は炉心溶融した3号機からの燃料取り出しは14年末に始める予定だったが、約4年遅れの今年4月に始まった。炉心溶融に至らなかった4号機ではすでに全量を取り出している。 廃炉で作業が最も難しいとされるデブリの取り出しは21年にまず2号機から始める。1~3号機では、原子炉圧力容器やその外側の格納容器にデブリがたまっている。総量は900トン程度と推計されているが、詳細な量や成分は分かっていない。放射線量が高く人が近づくことはできないため、作業は遠隔となり難航が予想される。 日々発生している放射性物質に汚染された水を巡っては、発生量を現在の1日平均170トン(18年度)から20年中に150トンに減らす目標を掲げてきた。改定案では発生量を最小限に抑える方針を示したが追加の数値目標は出さなかった。 個別の工程は当初計画より遅れているものも多い。3号機の燃料取り出しの遅れのほか、足元でもトラブルが頻発している。 8月に始まった1、2号機の排気筒解体では、装置のトラブルなどでたびたび作業が中断した。排気筒下にある汚染水をためる箱からは、一部が地中に漏れ出た恐れが出ている。予定通り廃炉を終えられるかは不透明だ。 全文
徹底解説!廃炉が遅れる真の理由(上) 作業員事故死、下がらぬ放射線量 via 産経ニュース
政府と東京電力は6月、福島第1原発の廃炉に向けた中長期ロードマップ(工程表)を2年ぶりに改定した。原子炉建屋にある燃料貯蔵プールからの燃料取り出しを最長3年遅らせるなど、後ろ向きの内容が目立ち、故郷への帰還を願う福島の住民にマイナスのイメージを与えたかもしれない。事故から4年以上たっても、なぜしっかりとした廃炉工程が定まらないのか。なぜ今になって工程を遅らせなければならなかったのか。その真の理由を探った。(原子力取材班) […] 平成23年12月に策定された工程表の改定は、25年6月以来2年ぶり3回目。今回の改定に際し、広瀬社長が「安全の配慮」に言及しなければならなかったほど、これまでは「スピード重視」が優先し、安全への配慮が十分だったかは疑問視される。 ただ、福島の住民に早く安心感を持ってもらうためには、廃炉を早期に達成する目標は致し方ない部分もあったことも否めない。 ところが、スピード重視は作業員の負担にもなっていた。 今年1月には、第1原発構内でタンク(高さ約10メートル)の設置作業中に、作業員=当時(55)=が落下し死亡した。第2原発でも機材に頭を挟まれ作業員=同(48)=が死亡したため、原発での全作業をいったん中止。工程を守ることに固執して、逆に工程の遅れを招いた。 […] 第1原発での作業員は当初3000人程度だったが、汚染水を入れるタンクの増設などで急増し、現在は約7000人が働く。 現場の環境変化により、どこにどういったリスクがあるかを見極め、工程を遅らせるのは当然である。 「。。。」それは3号機の燃料貯蔵プールからの燃料取り出しだ。建屋上部にあるプールには燃料が566体あり、それを撤去することはリスクの大幅低減となる。 3号機は23年3月の事故時に、水素爆発で建屋が大破した。建屋上部にはがれきが積み上がり、その撤去作業に時間がかかっている。 特に、建屋の除染が難航し、放射線量が思ったより下がらないことが工程にブレーキをかけた。このため燃料取り出しは従来の工程より約30カ月遅らせて29年度からとした。 […] 1号機にある392体の燃料、2号機にある615体の燃料の取り出しについても、線量低減など追加の安全対策を反映し、開始時期を29年度から32年度に変更している。 1号機ではいま、建屋カバーの本格的解体工事に着手している。昨年7月に解体を始める計画だったが、3号機でがれきを撤去した際に放射性物質が飛散した問題があり大幅に遅れていた。 飛散防止剤を散布しながら、建屋の周囲に防風シートを設置し、放射性物質濃度の24時間監視を図るなど、地元の不安を招かないように万全な体制を敷いている。 原子力規制委員会の田中俊一委員長は会見で、「リスク低減の中でも、燃料をできるだけ早く速やかに地上に降ろすことはかなり最優先事項になっている。3号機のリスクがやはり大きい。まだまだ先の見通しが得られた状況ではないと思う」との見解を述べた。 もっと読む。