Shuttering Monju reactor to take 375 billion yen and 30 years via The Asahi Shimbun

At least 375 billion yen ($3.2 billion) will be needed over 30 years to decommission the Monju prototype fast-breeder reactor in Fukui Prefecture, according to a government estimate revealed on Dec. 19.

The mind-numbing estimate and time frame were announced by the government’s committee for fast reactor development.

The committee’s proposed plan is to start decommissioning from 2017 and spend five and half years removing spent nuclear fuel from the problem-plagued reactor and complete the entire process in 2047.

The government also met with Fukui Governor Issei Nishikawa at the science and technology ministry building in Tokyo later the same day and passed on its intention to decommission the Monju reactor without a restart.

[…]

The government plans to finalize the decision to decommission Monju at a meeting of Cabinet members involved in nuclear energy policy, which is expected to be held Dec. 20 or later.

The estimated breakdown of the decommissioning costs are 225 billion yen for the maintenance cost of the facility until the completion of the process; 135 billion yen for deconstruction and other related costs; and 15 billion yen for preparation for the removal of spent fuel.

Read more at Shuttering Monju reactor to take 375 billion yen and 30 years

Related article: